An analysis of past maintenance costs indicates that maintenance cost is an average of $0.20 per machine-hour at an activity level of 10,000 machine-hours and $0.25 per machine-hour at an activity level of 8,000 machine-hours. Assuming that this activity is within the relevant range, what is the total expected maintenance cost if the activity level is 8,700 machine-hours? A. $2,000 B. $400 C. $2,250 D. $1,740